牧夫天文网

 找回密码
 加入牧夫(请注明天文爱好者,否则无法通过审核)

QQ登录

只需一步,快速开始

[新闻] 火星快车将完成第一次在轨检查

[复制链接]
Melipal 发表于 2003-7-5 17:14 | 显示全部楼层 |阅读模式 来自: 天津市 联通

马上注册,结交更多好友,享用更多功能,让你轻松玩转社区。

您需要 登录 才可以下载或查看,没有账号?加入牧夫(请注明天文爱好者,否则无法通过审核)

x
ESA's Mars Express first check-out nearly complete

2 July 2003
ESA's Mars Express spacecraft is progressing further every day on its journey to the Red Planet. Everything is set for arrival at Mars on the night of 25 December 2003, after a journey of about 400 million kilometres. In the weeks since its launch, engineers have started to thoroughly test the spacecraft and its equipment.

This testing phase is standard for all spacecraft on the way to their destination. Known as commissioning, it began 3 weeks after the launch. During this time, ground controllers sent signals to each of the orbiter's seven instruments to switch them on and verify their health status.
As well as commissioning the instruments, the ground controllers also tested each of the spacecraft抯 subsystems. There was a thrilling moment when one of the on-board computer memory units, known as the Solid State Mass Memory (SSMM), seemed to not respond properly during the instruments check-out. Good progress has been made on this issue in the last few days: a test involving all instruments was completed successfully by recording and recovering the data through the SSMM.

Unfortunately, during the commissioning of the power subsystem, ground engineers recorded an interconnection problem between the solar arrays and the power conditioning unit on board the spacecraft. This means approximately 70% of the power generated by the solar arrays is available for the satellite and its payload to use. This anomaly has no effect on the state of the spacecraft and has no impact on the mission during the whole trip to Mars, including the orbit insertion phase once at destination.

Despite this, the experts analysing the anomaly believe that even with this power shortage, the nominal Mars observation mission will be achievable. However, satellite payload operations may have to be reviewed for certain short periods of the mission.

Ground engineers are now preparing for the last of the payload抯 tests: the Beagle-2 lander will undergo its check-out on 4-5 July 2003. The experts are looking confidently to it. "In fact," says Rudolf Schmidt, Mars Express Project Manager, "overall, the spacecraft is in good shape. We are simply getting to know its personality."

For more information, please contact:

Rudi Schmidt, ESA Mars Express Project Manager
ESA-ESTEC
Tel: +31 (0)71 565 3603
E-mail: rudolf.schmidt@esa.int

本版积分规则

快速回复 返回顶部 返回列表